AI’s Water Footprint: Data Centre Water Use is More Complex Than Metrics Show
Data centres are expanding rapidly to meet demand for artificial intelligence and cloud services, increasing pressure on water, energy, and other infrastructure in the regions that host them. But standard data centre metrics do not always tell the full story. Alongside water used for on-site cooling, significant water consumption takes place upstream through the electricity generation that powers data centres. In contexts where water scarcity, both for human consumption and industrial operations, is a key concern, especially during droughts which are becoming more frequent and severe with climate change, water consumption of data centres is critical.
Data centre operators, businesses, investors, and host communities need to consider the full water footprint of data centres – including both on-site and off-site consumption – when assessing the risks and impacts of new capacity.
The True Water Footprint of AI
The International Energy Agency projects that data centre electricity consumption will more than double by 2030 in its Base Case scenario.
Water use is an important, and often overlooked, part of the picture. The most widely used water efficiency metric, water usage effectiveness (WUE), measures only the water consumed on site (for example, to cool), not the water used to generate the electricity that powers a facility. Research on African data centres finds this type of water use is typically the larger share of the total water footprint.
For data centres, and the businesses that rely on them through the digital services they build and buy, this could mean underestimating their exposure to water-related hazards and the ecological footprint of their business practices.
Read on to explore the scale of the risks and recent developments around the world—from South Africa, Malaysia, and Brazil—and practical steps businesses are taking to understand and manage these risks.

Key Developments
- The United Nations University estimates that 9.3 trillion litres of water will be needed to generate enough electricity for data centres to consume in 2030 to keep up with growing demand.
- In South Africa in July 2026, Cape Town’s Municipal Planning Tribunal gave first approval to two proposed data centres covering more than 120,000 m². The application did not specify their expected water use, highlighting the need to understand resource requirements as data centre capacity expands.
- Malaysia has published national guidelines on water and energy efficiency for data centres. Its Data Centre Task Force is reported to be approving projects only where power and water supplies have been secured.
- On 15 September 2026, Brazil’s president signed REDATA, a tax regime for data centres that requires on-site WUE of 0.05 litres per kilowatt hour or lower.


Why This Matters
In June 2026, the United Nations University Institute for Water, Environment and Health published an assessment of AI’s environmental footprint. It estimated that 9.3 trillion litres of water will be needed to generate enough electricity to meet the projected demand from data centres by 2030. This does not include on-site water usage, such as cooling. That is almost enough water to meet the minimum annual domestic water needs [20 litres per person per day] of all 1.3 billion residents of Sub-Saharan Africa for a full year.
The same report estimates that data centres consumed 448 TWh of electricity in 2025 and puts the associated land footprint at more than 14,500 km². Its central finding is that assessing carbon alone overlooks the water and land impacts of AI, which are felt locally.
For businesses, these impacts can mean competition for water with agriculture and households, pressure on local power grids, and regulatory and reputational exposure in host regions. (Learn more about the climate risks to technology and data security.)

Who Invests and Who Supplies the Water


Data centres bring investment, skilled employment, and digital infrastructure that host countries are seeking. In Malaysia, data centre and cloud computing projects accounted for RM95.8 billion (US$22.8 billion), close to 44% of all approved investment, in the first half of 2026, according to the Malaysian Investment Development Authority. Across the economy, foreign investment made up 58.1% of approved investment during the same period, led by the United States at RM33.1 billion (US$7.9 billion), Singapore at RM25.9 billion (US$6.2 billion), Japan at RM22.3 billion (US$5.3 billion) and China at RM16.5 billion (US$3.9 billion). In Cape Town, the proposed facilities would be built by the US-based Equinix, part of the company’s US$438 million plan to expand into South Africa’s AI market.
The services delivered by these facilities can support customers globally. However, the land and resource costs needed to supply them are felt locally.
This creates tensions with local communities, businesses, public services, and households. Understanding expected resource use is critical for business leaders and policymakers looking to propose and assess new data centre projects. (Read more about the climate risks to financial management and capital allocation.)
Cape Town: Approval Without a Water Figure
On 14 July 2026, Cape Town’s Municipal Planning Tribunal approved a land use application for two data centres covering 120,000m² to be built by Equinix near the airport, despite the application failing to state how much water or energy the facilities would use.
The Legal Resources Centre, representing objectors, lodged an appeal on 14 September 2026, stating that this omission made the application “impossible for it to be properly considered”. Attorney Kimal Harvey, presenting for the objectors, estimated the facilities’ electrical demand at about 174 MW and cited research suggesting a data centre using traditional cooling consumes about 25.5 million litres of water a year per MW. These are the estimates presented by the objectors, not disclosed figures.

South Africa has an arid to semi-arid climate; the country’s Department of Water & Sanitation’s National Water Resource Strategy reported annual rainfall averaging 465 mm (half the global average), and states that the country “is fast approaching full utilisation of available surface water yields”.
The approval of the data centre is a first step: the Site Development Plan and building plans still require scrutiny. The decision now rests with Cape Town’s executive mayor, who acts as the appeals authority. See how businesses are managing their compliance and legal exposure.
Africa: Power Source Matters More Than Climate
Hot, dry climates are often assumed to make data centres more water intensive. But evidence from Africa suggests that the source of electricity powering a data centre matters more than the climate it operates in.
Researchers at Carnegie Mellon University Africa and UC Riverside analysed water efficiency across data centres in 41 African countries, with 11 analysed in detail. In 11 of those countries, data centres used less water than the global average for the same AI task.

The researchers attribute much of this to the electricity mix. Most data centre water consumption is indirect, occurring during electricity generation. In Algeria, Tunisia, Egypt, and Libya, this process uses a combined-cycle (combining gas and steam) using an average of 0.795 litres of water per Kwh, compared to the global average of 1.58L/Kwh for gas-only generation.
The picture changes where electricity is dominated by hydropower.
Ethiopia and the Republic of the Congo draw 95.7% and 99.6% of their electricity from hydropower and were the only two countries analysed where water consumption for data centres exceeds the global average. Evaporation from reservoirs makes hydropower a water-intensive energy source.
The study concludes that in the case of data centres, water consumption is more strongly linked to power generation than to the regional climate alone—with practical implications for data centre site selection. Learn how businesses are making climate and nature part of their long-term strategic choices.
According to the same study, water-loss due to leakage from distribution networks is estimated to average 46% across Africa, compared with around 39% globally, and exceeds 61% in Nigeria. For data centre operators, understanding the existing network losses alongside new demand will be an important consideration when assessing local water availability and infrastructure resilience.

Malaysia: Rules Before the Largest Facilities Are Built
In the southern Malaysian state of Johor—located just across the strait from Singapore—the data centre sector is expanding rapidly, bringing growing demand for both water and electricity.
In the state, data centres use around 9.07 million litres a day, or 0.6% of the state’s total consumption, and demand is expected to grow. Across peninsular Malaysia, peak electricity demand for data centres reached 849 MW in December 2025 and is projected to reach 4,811 MW by 2030.


Here’s how Malaysia is responding:
- In August 2025, the Johor government announced plans for up to 12 million litres a day of treated wastewater to supply a reclamation plant supporting data centre cooling.
- National guidelines from the Ministry of Investment, Trade and Industry set power usage effectiveness thresholds of 1.4 or below for hyperscale facilities and 1.6 or below for purpose-built colocation facilities, alongside a 2.2 m³/MWh WUE (water-usage effectiveness) upper threshold. Johor has set a stricter WUE threshold of 1.8, matching Singapore’s standard.
- As of August 2026, the Data Centre Task Force was also reported to be clearing projects only where power and water supplies are secured and green compliance can be demonstrated.
The thresholds are guidelines rather than an established enforcement record, but they provide published standards for investors and communities before the largest facilities are built.
For businesses planning new capacity in Johor, this means water and energy availability, efficiency, and compliance need to be considered early in the development process.
Brazil: A Strict Limit on Cooling Water
Brazil is taking a different approach to managing data centre water use.
On 15 September 2026, Brazil’s president signed REDATA, a special tax regime for data centre services that provides tax incentives for qualifying equipment purchases and imports.
To qualify, a facility must:
- source all its electricity from renewable or low-emission generation;
- publish a sustainability report covering its water use and power sources;
- direct at least 10% of its capacity to the Brazilian market;
- invest 2% of acquired asset value in domestic research with universities or research institutes; and
- keep WUE at or below 0.05 litres per kilowatt hour, measured annually.

This WUE limit is about 44 times lower than Malaysia’s national guideline and 36 times lower than Johor’s threshold. It is also below the average on-site WUE reported for Microsoft Azure (0.30 L/kWh) and AWS (0.18 L/kWh).
As with Malaysia’s guidelines, the WUE limit covers on-site water only.
REDATA’s energy condition allows low-emission generation, which can include hydropower—a water-intensive source. Businesses assessing facilities under either regime should therefore look at both on-site water use and the power supply.
What Businesses Can Do
Procurement and IT leaders
- Ask providers for both measures. Request on-site WUE and the source and water intensity of the electricity supplying the facility.
- Treat model choice as a resource decision. The African dataset estimated that writing a ten-page report used about 0.66 litres of water with Llama-3-70B and about 59 litres with GPT-4. The authors describe these as 2024 reference values, not current performance.
- Consider where models run. A 2025 benchmarking study of 30 models estimated that DeepSeek-R1 used 29.1 Wh and over 200 ml of water on its own infrastructure, compared with 7.4 Wh and 34 ml on Microsoft Azure. These are modelled estimates, not metered measurements.
Sustainability and reporting leads
- Report on-site and electricity-related water separately, so that improvements in cooling are not mistaken for reductions in the total footprint.
- Check water sources. Drinking water, treated wastewater, and groundwater carry different risks. Research notes that data centres commonly consume around 80% of the freshwater they withdraw, compared with roughly 10% for typical households and offices.

Site selection and supply chain leaders
- Include the electricity mix in site selection, as it can affect the water footprint more than local climate.
- Secure supply before approval. Follow Malaysia’s reported practice of confirming power and water supplies before projects proceed, and use treated wastewater where available. Learn more about how businesses are keeping essential utilities and process inputs stable and reliable.
- Agree drought priorities in advance. Establish, in writing, how water will be allocated between the facility, agriculture and households if supply is constrained.

Operations and continuity teams
- Plan for disruption to digital services. Where customer-facing systems depend on data centres in water- or power-stressed regions, build in redundancy and backup arrangements. See what businesses are already doing to manage nature and climate risks to technology and information systems.

Measure Your Own Digital Footprint
Many organisations have not yet measured the footprint of their own digital estate. Digital Impact for Species, a free tool built by the Nature & Climate Impact Team at the University of Exeter, estimates the carbon footprint of any web page in seconds. First launched at the World Economic Forum in Davos, it helps organisations test their own websites and gives practical guidance to make them lighter.
What You Can Do?
Read More From the Global Risks Category
- Latest News
Caption Text Swiss Glaciers Have Lost Almost 20% of Their Ice Since 2021
A winter with very little snowfall followed by intense heatwaves from May to September left glaciers without their protective... - Latest News
Caption Text Rooftop Revolution in France: Why Big Buildings Are Going Green
France is making rooftops part of its response to climate change. Instead of treating roofs as unused building space, new... - Latest News
Caption Text Half of Europe Experienced Very Strong Heat Stress During Summer 2026
More than half of Europe experienced very strong heat stress at some point during summer 2026, as repeated heatwaves pushed temperatures... - Latest News
Caption Text Europe’s Climate Change Bill Is Growing
Climate change is already creating a growing financial burden across Europe. Between 1980 and 2024, weather and climate related... - Latest News
Caption Text By 2030, Most Families in Ethiopia, Malawi, and Nigeria Won’t Be Able to Afford a Healthy Meal
By 2030, more than 90% of people in Malawi and Nigeria, and 75% in Ethiopia, won’t be able to... - Latest News
Caption Text Global Rivers Are Losing Oxygen as the Climate Warms
Rivers around the world are losing dissolved oxygen, an essential condition for healthy freshwater ecosystems. A 2026 study published in Science Advances analysed 21,439...